Draft Delivery Agreement for the Bannau Brycheiniog (Brecon Beacons) National Park Local Development Plan 2025 - 2045

Ends on 26 June 2025 (48 days remaining)

Appendix 2: Detailed timetable for each stage of the LDP Comment

Timetable

Stage

Key decision milestones

Definitive timetable

1.

September 2025 - February 2027 [Months 1 – 18]

September 2025 – February 2026

[Months 1 – 6]

February & March 2026

[Months 6 & 7]

Participation and involvement: strategy and evidence.

Decision making frameworks.

Call for candidate sites

Authority [date to be confirmed November 2025] to agree consultation on:

  • Statutory baseline scoping consultation [Environmental Report]

Methodologies:

  • Candidate Sites Assessment;
  • Sustainability Appraisal; and,
  • Approach to evidence.

2.

February & March 2027

[Months 18 & 19]

Preferred strategy consultation – 6 Weeks

National Park Authority [date to be confirmed February 2027] to agree consultation on Preferred Strategy.

3.

April - November 2027

[Months 20 – 27]

Setting the deposit plan

Considering representation made on the preferred strategy to inform content of the full draft Plan.

4.

December 2027 – January 2028

[Months 28 & 29]

Deposit consultation – 6 Weeks

National Park Authority [date to be confirmed November 2027] to agree consultation on Deposit Plan.

Indicative timetable

5.

February – July 2028

[Months 30-35]

Preparation for submission and pre-examination changes consultation

National Park Authority [date to be confirmed

[May 2028 to agree pre examination changes for consultation]

[July 2028 to agree submission of the Plan].

6.

August 2028 - July 2029

[Months 36 – 47]

Examination

Plan examined in public by an independent Planning Inspector (Planning Environment Decisions Wales) – May involve consultation on 'Matters arising changes'.

7.

August/ September 2029.

[Months 48/ 49].

Inspector's Report and Adoption

National Park Authority [date to be confirmed September 2029] to adopt the Plan.

Monitoring

First Annual Monitoring Report published 31 October 2031 and annually thereafter.