Draft Delivery Agreement for the Bannau Brycheiniog (Brecon Beacons) National Park Local Development Plan 2025 - 2045
Appendix 2: Detailed timetable for each stage of the LDP Comment
Timetable |
Stage |
Key decision milestones |
|
Definitive timetable |
|||
1. |
September 2025 - February 2027 [Months 1 – 18] September 2025 – February 2026 [Months 1 – 6] February & March 2026 [Months 6 & 7] |
Participation and involvement: strategy and evidence. Decision making frameworks. Call for candidate sites |
Authority [date to be confirmed November 2025] to agree consultation on:
Methodologies:
|
2. |
February & March 2027 [Months 18 & 19] |
Preferred strategy consultation – 6 Weeks |
National Park Authority [date to be confirmed February 2027] to agree consultation on Preferred Strategy. |
3. |
April - November 2027 [Months 20 – 27] |
Setting the deposit plan |
Considering representation made on the preferred strategy to inform content of the full draft Plan. |
4. |
December 2027 – January 2028 [Months 28 & 29] |
Deposit consultation – 6 Weeks |
National Park Authority [date to be confirmed November 2027] to agree consultation on Deposit Plan. |
Indicative timetable |
|||
5. |
February – July 2028 [Months 30-35] |
Preparation for submission and pre-examination changes consultation |
National Park Authority [date to be confirmed [May 2028 to agree pre examination changes for consultation] [July 2028 to agree submission of the Plan]. |
6. |
August 2028 - July 2029 [Months 36 – 47] |
Examination |
Plan examined in public by an independent Planning Inspector (Planning Environment Decisions Wales) – May involve consultation on 'Matters arising changes'. |
7. |
August/ September 2029. [Months 48/ 49]. |
Inspector's Report and Adoption |
National Park Authority [date to be confirmed September 2029] to adopt the Plan. |
Monitoring First Annual Monitoring Report published 31 October 2031 and annually thereafter. |